Case Studies
Factory Relocation & Plant Decommissioning Project
Back to Case StudiesFactory Relocation Project, Part Plant Decommissioning, Dismantling and Removal. RRS Group were chosen to manage the entire project and act as Principle Contractor under the CDM Regulations 2015. The project was approx. four months in duration and split between two distinct time plans with a break in between. RRS Group supplied all skilled site personnel, a full-time project engineer and all machinery lifting and moving plant, equipment and transport. The project consisted of the dismantling and removal of:
- Vertical Stack Fans
- Board Line
- Tenona Line
- Dust Collection Plant
- Suction Ductwork
- All Hoppers, Feeders and Filter Plant
- Conveyors
- Control Panels, Distribution Boards
- Paint Application Plant
- Platforms and Mezz Floors
- Decommissioning of all Pipework
- Management of Capping off of Natural Gas and Towns Water services
If you have a factory relocation project get in touch?
Back to Case Studies